The Ledger
Pennsylvania, the energy economy in miniature
Nov 26, 2026

One state holds the whole story. Pennsylvania produces the gas, hosts the nuclear plants, runs the grid operator's territory, collects the fees, and sends its residents the higher electric bills — all at once. If you want to understand how energy, the stock market, inflation, state revenue, and GDP connect in America right now, start here.
THE SIZE OF IT
Pennsylvania's economy was $1,056.5 billion in 2025, the sixth largest in the country, 3.4% of the United States. Output per person was $80,898. Real growth — after inflation — was 1.8% in 2025, and nominal growth 4.7%. By the first quarter of 2026 the economy was running at about a $1.097 trillion annual rate. Unemployment sits at 4.3%, median household income near $77,500.
That growth rate is the first dot. The United States grew 2.5% in the first quarter of 2026, 2.2% in the second, 3.4% in the third. Pennsylvania, at 1.8% real for 2025, is growing slower than the country it powers. Hold that thought — it comes back at the end.
ENERGY: THE GAS, THE ATOMS, AND THE DATA CENTERS
Pennsylvania produced about 21.65 billion cubic feet of natural gas a day in August 2026 — 17% of all US output, second among the states, up 3.8% from a year earlier. The Marcellus Shale underneath it produces about 27 billion cubic feet a day, roughly a third of all US shale gas, and the wider Appalachian basin about 36.6 billion, about 31% of US marketed gas. It is the lowest-cost gas basin in the country.
But the second quarter of 2026 told a different story: production fell 1.6% from a year earlier to 1,925 billion cubic feet, the lowest quarterly volume since late 2024, and the number of new horizontal wells fell too. The basin is not growing the way it was. Meanwhile the price of gas sold to Pennsylvania households rose 7.3% in the same quarter.
Nuclear is the second leg. Unit 1 at Three Mile Island, closed in 2019, is being restarted as the Crane Clean Energy Center: 835 megawatts, a $1.6 billion restart, all of it sold to one technology company under a 20-year contract, with a target of 2027. The catch is the grid connection: transferring interconnection rights from older generators near Philadelphia is contested, and without it, full output could slip to 2030 or later. Amazon, meanwhile, has contracted for most of the power from the Susquehanna nuclear plant, ramping to 1,920 megawatts by 2032. And in Indiana County, the Homer City site — where a two-gigawatt coal plant closed in 2023 — is being rebuilt as a 4.5-gigawatt gas plant, which would be the largest in the country, to power a data-center campus, with first power targeted for 2027.
The data centers are the third leg, and the biggest. One count puts 303 data centers in Pennsylvania as of mid-November: 17 operating, 12 under construction, 274 planned, nine of them at a gigawatt or more. Amazon alone announced at least $20 billion for campuses in Luzerne and Bucks counties, creating at least 1,250 jobs. The utility serving central and eastern Pennsylvania reports a data-center pipeline of 28.3 gigawatts — 31.8 gigawatts in advanced planning alone — with about 10 gigawatts under signed service agreements and 5 gigawatts already being built, and a $23 billion grid-investment plan for 2026 to 2029 to connect it all.
THE GRID BILL: WHERE THE DOTS MEET THE HOUSEHOLD
Pennsylvania sits inside PJM, the grid operator for 13 states and Washington, covering 67 million people. PJM's capacity market pays generators to be ready, and its price is where the data-center boom lands on household bills. The numbers are stark. The capacity price was $28.92 per megawatt-day for 2024/25. Then $269.92. Then $329.17, hitting the approved cap. Then $333.44, hitting a raised cap. The latest auction, for 2028/29, cleared at the $325 cap — and still fell about 6.8 gigawatts short of the reliability requirement. Without the cap, prices would have reached nearly $555 and cost about $29.7 billion.
Data centers are the driver: about 40 to 46% of capacity costs in recent auctions, $6.5 billion of $16.4 billion in the December 2025 auction alone, $21.3 billion of $47.2 billion across the last three. PJM forecasts that 30 of the 32 gigawatts of new load by 2030 is data centers and AI. The pass-through to Pennsylvania households is roughly $15 to $30 a month. Pennsylvania negotiated the price cap with PJM, later extended through 2030; the state says the cap prevented an extra $13.3 billion in consumer costs in the latest auction alone.
This is the inflation channel, and it is specific to this state. National inflation is services and shelter. In Pennsylvania, it is also the electric bill: capacity charges up elevenfold in four years, residential gas prices up 7.3% in a year. The AI boom does not just raise asset prices. It reprices the power itself.
THE STOCK: THE REPRICING, IN ONE TICKER
Constellation Energy, the company restarting Three Mile Island and operating the country's largest nuclear fleet, traded at $235.22 on the morning of November 25, down almost 4% on the day. It is down 33% this year and 34% over twelve months, against a 52-week high of $380.78 last December. Market value is about $89 billion.
And yet the business beat: third-quarter earnings of $5.06 a share on $9.55 billion in revenue, guidance of $11 to $12 a share for the year, growth above 20% a year through 2029, and an analyst consensus target near $383 — more than 50% above the current price. One bank raised its target to $393 just two days ago, and the stock still fell.
That is the same repricing as the gas-turbine maker whose stock fell 40% from its July high while its backlog hit $197 billion. The market spent 2024 and 2025 paying for the AI power story. In November 2026 it started asking for contracted revenue instead of announcements — and for proof the grid connection will actually arrive. The Crane restart's target is 2027; the interconnection risk runs to 2030. The gap between those two dates is what the stock is pricing.
The turbine maker is the other half of the Pennsylvania stock story, and it never appears in the state's numbers: every gas plant in the Homer City mold needs turbines, and turbines are sold out — a backlog near 116 gigawatts, a heavy-duty unit ordered today arriving in 2031. Pennsylvania's gas becomes someone else's power-plant order book.
STATE REVENUE: THE GAS PRICE IS THE SWING FACTOR
Pennsylvania ended its 2025-26 fiscal year with $48.9 billion in General Fund collections, $1.1 billion — 2.4% — above estimate. Sales tax brought in $15.5 billion, personal income tax $20 billion, corporation tax $7.4 billion. The Motor License Fund added $3.2 billion.
The gas money is smaller and more volatile. The state charges an annual impact fee on unconventional wells, and the fee rises and falls with the gas price. For 2025 it collected $243.9 million, up $79.3 million — 48% — from 2024, because the average gas price rose 51% to $3.43, and 444 new wells were drilled, the most since 2022. The average fee per well rose to about $19,000 from $13,560. The cumulative total since 2012 is now above $3.12 billion, split $133.8 million to drilling counties and municipalities, $89.2 million to the Marcellus Legacy Fund, and $20.9 million to state agencies.
But read the path, not just the year: $278.9 million in 2022, then $179.6 million, then $164.6 million, then $243.9 million. The fee is a gas-price derivative. And it is small against the whole: $243.9 million is half of one percent of a $48.9 billion General Fund. Gas does not fund Pennsylvania. It funds the drilling counties and the Legacy Fund. The real fiscal question is whether the data-center build-out broadens the income and corporation tax base — and whether that happens faster than the state's structural deficit spending eats the surplus.
CONNECTING THE DOTS
Here is the loop, in one paragraph. Pennsylvania's cheap gas feeds gas plants and, through the grid, data centers. The data centers bid up capacity prices elevenfold, which raises household bills and hands the state a political problem it answered with a price cap and new data-center rules. The same AI demand lifts gas prices, which lifts the impact fee 48% and helps the General Fund beat its estimate by $1.1 billion. The stock market, meanwhile, has stopped paying for the story and started discounting the delivery risk — the nuclear restart that might slip to 2030, the turbines that arrive in 2031, the transformers that take three years.
And the questions that loop leaves open:
1. Does the boom lift Pennsylvania's growth rate, or just its asset prices and its utility bills? Real GDP grew 1.8% while the country grew faster. Amazon's $20 billion brings 1,250 jobs. This is capital-intensive growth, not job-intensive growth, and the GDP number will tell us which one it is.
2. Who pays for the grid — the data centers or the households? The cap and the new large-load rules are the state's answer so far: make the new load bring its own generation or pay its own way. Whether that holds when 274 projects are in the pipeline is the fight of the next three years.
3. What happens when the gas price falls again? The impact fee fell by more than 40% from 2022 to 2024 on price alone. A revenue line that doubles and halves with a commodity price is not a foundation. It is a windfall with a mailing address.
4. What is the constraint that actually binds? The state has the gas, the nuclear sites, the land, and the buyers. What it does not have is the grid capacity, the transformers, or the interconnection queue to move the power. The bottleneck is not supply. It is connection — and connection is the slowest thing in the system.
Pennsylvania is not a side story to the AI economy. It is the place where the AI economy meets the physical world: the gas has to be drilled, the plant has to be built, the wire has to be strung, the bill has to be paid, and the revenue has to be counted. Every other state in the AI build-out will learn what Pennsylvania learns first — that the constraint was never the demand. It was everything between the demand and the meter.
Sources: state GDP; Pennsylvania gas production; the nuclear restart; state revenue and impact fees; the capacity market; Pennsylvania data centers.
https://worldatscale.com/economy/gdp-by-state/
https://worldoilmonitor.com/pennsylvania-natural-gas-production
https://stockti.com/constellation-energy-surges-despite-regulatory-challenge-to-three-mile-island-restart
https://www.gurufocus.com/stock/CEG/summary
https://www.pa.gov/agencies/revenue/newsroom/revenue-department-releases-fiscal-year-2025-26-collections,-commonwealth-collects--1-1-billion-above-original-estimate
https://www.puc.pa.gov/press-release/2026/puc-announces-2438-million-in-natural-gas-impact-fees-for-pennsylvania-communities-06152026
https://theenergycollective.com/capacity-market/
https://www.phillytalks.com/2026/11/how-can-ai-data-centers-grow-when-power-is-short-and-residents-say-no/
— Priya